This gives you the likely route from the numbers, not a decision. Network operators differ, sites have their own constraints, and the final call is theirs. Nothing you enter leaves your browser.

G98 / G99 route assessment
Indicative route from the figures entered. Not a design or an approval.
| Input | As entered |
|---|---|
| Generation | |
| Supply | |
| Type testing | |
| Calculated | |
| Threshold | |
| Working |
G98 covers fully type tested micro-generators up to and including 16 A per phase (ENA Engineering Recommendation G98, Issue 2, 10 March 2025). Quoted timings elsewhere are commonly used norms rather than guarantees, and network operators differ. This is an indication for planning a job, not an approval: the operator handling the connection has the final say.
| G98 | G99 | |
|---|---|---|
| Applies to | Fully type tested micro-generators up to and including 16 A per phase | Generation above the G98 threshold, or anything not fully type tested |
| Roughly | About 3.68 kW single phase, about 11 kW across three phases | Anything larger, and all non-type-tested equipment |
| Order of events | Connect first, notify after. The install goes ahead, then the network operator is told | Apply first, connect after. Nothing is energised until approval comes back |
| What you send | A notification recording what was installed and where | A full application, assessed by the network operator |
| Typical timing | Notification within 28 days of commissioning | Commonly quoted around 45 working days for a decision |
| Risk to the job | Low. The work is done before the paperwork | Real. The connection date depends on someone else’s queue |
Comfortably under 16 A per phase, and type tested. Install, commission, then notify.
Above roughly 3.68 kW on a single phase, so it crosses the line. Apply before connecting.
An AC-coupled battery inverter counts toward the same per-phase total as the panels. Solar that passes on its own can push the premises over once storage is added.
Three phases raise the ceiling to about 11 kW in total, so this still sits inside G98.
G98 only covers fully type tested equipment. If the inverter is not on the ENA register with a Product ID, the G98 route is closed regardless of size.
These are demand, not generation, so G98 and G99 do not apply. They still need a network notification, but through the demand route rather than these two.
G98 is only open to fully type tested micro-generators. Every inverter needs to appear on the ENA Type Test Verification Report Register and be quoted by its Product ID. Substituting a different inverter on the day, for stock reasons, quietly invalidates the route you applied under.
The 16 A per phase limit is the aggregate for the premises, not the figure for the panels alone. A battery added later, or quoted as a separate job, can push a compliant solar install over the line without anyone revisiting the paperwork.
Per phase means per phase. A three-phase supply raises the ceiling to roughly 11 kW in total, but only if generation is actually balanced across the phases rather than sitting on one.
Applications bounce on file sizes, missing serial-number shots and unreadable commissioning certificates far more often than on anything electrical.
On the G98 route the work is already done, which makes the notification easy to forget. It is still a requirement, and a missing one surfaces later at the worst moment, usually when the customer applies for an export tariff.
Check the source, and check with your operator. The scope above is set by ENA Engineering Recommendation G98, Issue 2, dated 10 March 2025, which covers the connection of fully type tested micro-generators up to and including 16 A per phase. Quoted timings are the commonly used norms rather than a guarantee, and network operators differ. The recommendations themselves are published by the Energy Networks Association, and applications are submitted through ENA Connect Direct.
installHUB captures the connection data during the site survey and files the notification through ENA Connect Direct without anyone re-keying it, then tracks the operator’s response against the job it belongs to. The survey answers become the application fields.
A G99 application is the request you submit to the network operator before connecting generation that sits above the G98 threshold, or that is not fully type tested. Unlike the G98 route, nothing is energised until the operator has assessed the application and approved it. It is named after ENA Engineering Recommendation G99, which sets out how that connection is made.
The threshold. G98 covers fully type tested micro-generators up to and including 16 A per phase, which is roughly 3.68 kW on a single phase or about 11 kW across three. Below that line you connect first and notify the operator afterwards. Above it, or with equipment that is not fully type tested, you apply under G99 and wait for approval before connecting.
Around 45 working days for a decision is the figure most commonly quoted, but it varies by network operator and by how loaded the local network already is. Treat it as a lead time to plan the job around rather than a fixed date, and confirm the current position with the operator handling the connection.
Battery storage that can export counts as generation, and an AC-coupled battery inverter counts toward the same 16 A per phase total as the solar. That is the most common way a site crosses the line: the panels pass on their own, the battery is quoted separately, and the combined figure has never been checked against the threshold.
No. G98 and G99 cover generation. An EV charge point or a heat pump is demand, so it goes through the network operator’s demand notification route instead. It still needs notifying, which is why it is easy to assume the same forms apply.
On the G98 route the installation is already live, so nothing fails immediately, and that is exactly why it gets missed. The obligation stands, and the gap usually surfaces later, most often when the customer applies for an export tariff and the supplier asks for evidence the connection was notified.
Through ENA Connect Direct, the shared portal the network operators use for connection applications and notifications. installHUB submits to it directly from the job, so the survey data becomes the application without being re-keyed.